Unit-Time Job Scheduling


Unit-time job scheduling assigns jobs of duration one to time slots on a given number of identical machines. In the precedence-constrained problem, an acyclic digraph specifies which jobs must finish before others start. Each graph vertex represents a job and each directed graph edge (u,v) requires job u to precede job v. A job occupies one machine for its entire slot.

With m machines and n jobs, a schedule ending by slot T is a function tau:V->{1,...,T} such that at most m jobs have any one value of tau, and tau(u)<tau(v) for every directed graph edge (u,v). The objective is to minimize the final completion time, called the makespan. For three unrelated jobs on two machines, the minimum makespan is 2.


See also

Acyclic Digraph, Algorithm, Polynomial Time

Explore with Wolfram|Alpha

References

Levey, E. and Rothvoss, T. "A (1+epsilon)-Approximation for Makespan Scheduling with Precedence Constraints Using LP Hierarchies." SIAM J. Comput. 50, STOC16-201-STOC16-217, 2021. https://doi.org/10.1137/16M1105049.

Cite this as:

Weisstein, Eric W. "Unit-Time Job Scheduling." From MathWorld--A Wolfram Resource. https://mathworld.wolfram.com/Unit-TimeJobScheduling.html

Subject classifications